A 400 sq ft driveway at three thicknesses
Quantities include 10% order allowance. Illustrative 2027 budget inputs are $6.50 per 80 lb bag, $165 per delivered yard before fees, and $95 per US short ton of asphalt mix. Replace them with supplier quotes.
| Course | Order quantity | Material example | Separate costs |
|---|---|---|---|
| 4 in concrete | 5.43 yd³ or 245 bags | $896 bulk or $1,593 bagged | Short-load fee, forms, placing |
| 6 in concrete | 8.15 yd³ or 367 bags | $1,344 bulk or $2,386 bagged | Base, reinforcement, finishing |
| 3 in hot-mix asphalt | 7.98 short tons at 145 lb/ft³ | $758 mix | Base work, hauling, rolling |
Work up an installed slab budget
Example scope for a 400 sq ft ordinary slab. Confirm the total thickness and reinforcement with the project designer or local authority. Sample arithmetic does not prescribe a driveway design.
| Quoted item | Pricing basis | Example treatment |
|---|---|---|
| Installed slab | $6.50–$12.00 per sq ft scenario | $2,600–$4,800 for 400 sq ft |
| Unsuitable soil or demolition | Separate measured scope | Ask for disposal, haul and replacement-base charges |
| Finish and access | Specified labor and equipment | Describe broom finish, pumping distance and access |
Compare bagged and ready-mix at the same yield
A yard takes 45 bags at 0.60 cubic feet per 80 lb bag. At $6.50 each, the mix alone costs $292.50 per yard. If ready-mix costs $165 per yard plus a flat $175 dispatch fee, the cost lines cross near 1.37 yards. Actual minimum-load charges often vary by order size, and site labor can change the decision.
Separate thickness from preparation
When a quote says “4 inches,” ask whether that refers to concrete, asphalt or aggregate. Mark each lift separately. A thicker concrete section affects ordered yards, while a thicker aggregate section changes excavation and base quantities.
Arrange delivery before the crew arrives
Confirm truck access, chute reach, pump charges, the crew’s placement rate and short-load terms. Local mix requirements and exposure conditions belong in the order description, along with the measured quantity.