Concrete Slab & Driveway Cost Guide

Start with the finished surface area and thickness. A 6-inch slab uses 50% more concrete than a 4-inch slab with the same footprint. Excavation, aggregate, reinforcement, forming, delivery and finishing each have their own cost drivers, so ask for those items on separate lines.

A 400 sq ft driveway at three thicknesses

Quantities include 10% order allowance. Illustrative 2027 budget inputs are $6.50 per 80 lb bag, $165 per delivered yard before fees, and $95 per US short ton of asphalt mix. Replace them with supplier quotes.

A 400 sq ft driveway at three thicknesses
CourseOrder quantityMaterial exampleSeparate costs
4 in concrete5.43 yd³ or 245 bags$896 bulk or $1,593 baggedShort-load fee, forms, placing
6 in concrete8.15 yd³ or 367 bags$1,344 bulk or $2,386 baggedBase, reinforcement, finishing
3 in hot-mix asphalt7.98 short tons at 145 lb/ft³$758 mixBase work, hauling, rolling

Work up an installed slab budget

Example scope for a 400 sq ft ordinary slab. Confirm the total thickness and reinforcement with the project designer or local authority. Sample arithmetic does not prescribe a driveway design.

Work up an installed slab budget
Quoted itemPricing basisExample treatment
Installed slab$6.50–$12.00 per sq ft scenario$2,600–$4,800 for 400 sq ft
Unsuitable soil or demolitionSeparate measured scopeAsk for disposal, haul and replacement-base charges
Finish and accessSpecified labor and equipmentDescribe broom finish, pumping distance and access

Compare bagged and ready-mix at the same yield

A yard takes 45 bags at 0.60 cubic feet per 80 lb bag. At $6.50 each, the mix alone costs $292.50 per yard. If ready-mix costs $165 per yard plus a flat $175 dispatch fee, the cost lines cross near 1.37 yards. Actual minimum-load charges often vary by order size, and site labor can change the decision.

Separate thickness from preparation

When a quote says “4 inches,” ask whether that refers to concrete, asphalt or aggregate. Mark each lift separately. A thicker concrete section affects ordered yards, while a thicker aggregate section changes excavation and base quantities.

Arrange delivery before the crew arrives

Confirm truck access, chute reach, pump charges, the crew’s placement rate and short-load terms. Local mix requirements and exposure conditions belong in the order description, along with the measured quantity.